Week 2

First meeting of our group. Decide on a project and roughly how it will be implemented.

Week 3

Produce a project diagram with more detailed information on how modules will be split up.

Week 4

Decide on who will be implementing different modules and produce interfaces.  

Week 5

Install required software and begin planning designated modules in detail.  Start with skeletal implementation.

Week 6

Skeletal implementation should be finished with communication between modules implemented.

Week 7/8

Finish code for module and integration of module into system.

Week 9

Testing and  finish documentation.